Dutch chipmaker Nexperia and Tata Electronics announced a partnership on September 17, 2026 to make Nexperia’s chips in India, with financial terms not disclosed.
Nexperia plans to produce MOSFETs at Tata’s 300mm fab in Dholera, Gujarat, which is still being built, and assemble and test discrete semiconductors at Jagiroad, Assam, The Next Web reported. The two will also work together on technology. Details are based on The Next Web and TechNode Global.
What the partnership covers
| Site | Role |
|---|---|
| Dholera, Gujarat | Tata's 300mm fab, for Nexperia's MOSFETs. Under construction |
| Jagiroad, Assam | Assembly and test of discrete products |
| Joint work | Technology development and research |
| Financial terms | Not disclosed |
Why it matters
Randhir Thakur, CEO of Tata Electronics, said the company was “thrilled to partner with Nexperia”, and linked the deal to India’s growing trade ties with the European Union. Stefan Tilger, Nexperia’s interim CEO, said it reinforces a “resilient and globally balanced manufacturing network.”
Nexperia ships over 100 billion products a year, but that is the company’s global total, not the size of this deal. The company has been caught between Dutch and Chinese authorities since 2025.
The partnership adds to other chip projects in Gujarat and elsewhere. Micron plans to assemble and test hundreds of millions of chips at its Sanand plant next year, and Seoul Semiconductor has held early talks with states about an Indian plant. Tata Electronics separately confirmed a cybersecurity incident in June.
The Dholera fab has a longer road ahead. In July, before this partnership was announced, Bloomberg reported that India’s Technology Minister Ashwini Vaishnaw expected the fab to begin commercial operations in mid-2028, later than Tata’s earlier target of the end of 2026, and that it would start with 90nm chips, TrendForce reported. Tata’s technology partner for the fab is Taiwan’s PSMC, with 28nm the most advanced node planned.
Why it matters to the trade
Local production will take time, since the Dholera fab is not finished. For now, this does not affect prices or supply.
Correction (November 1, 2026): An earlier version presented 100 billion units as part of this deal. That is Nexperia's global annual shipments.